Cutting takes an hour in the fictional shop below. Reducing it to 30 minutes saves work, while the proposed customer receipt stays at Wednesday 10:00. The next operation still starts at its original booked time. The saved half-hour becomes additional waiting before that slot.
That result belongs to this particular calendar. To decide what a faster operation changes, follow the order through the remaining bookings and the assumed trip to the customer. Keep a missing date open rather than filling it with the finish you would like to see.
Set the boundaries before adding time
The Lean Enterprise Institute separates working time, full-process passage and customer wait. LEI’s time definitions
Our working record uses three explicitly chosen measures: processing minutes, production elapsed time from release to completed inspection, and the whole order from acceptance to assumed customer receipt. The calendar, calculations and worksheet are our fictional design, rather than an official LEI form.
For this record, the 30-minute final inspection is included in the processing total. That is an authored classification choice for the example. Dispatch waiting and transport sit outside its production boundary.
All times below are Toronto time across one invented Monday, Tuesday and Wednesday, with no clock change. We count elapsed hours, including overnight time. Those hours are not a measure of lost scheduled working time.
Follow the eight intervals in the base plan
One custom order moves through cutting, coating and final inspection in that sequence. Each stage needs the previous stage to finish. The later bookings remain fixed unless a branch expressly changes them. These are supplied planning inputs, not observed execution or evidence that a real carrier will meet a delivery time.
Order handling: Monday 08:00–09:00, 60 minutes. The order is accepted at 08:00 and released into the defined shop process at 09:00.
Cutting: Monday 09:00–10:00, 60 minutes. The entire cutting interval is included for this order.
Wait for coating: Monday 10:00–Tuesday 11:00, 1,500 minutes. That is 25 elapsed hours before the fixed coating booking.
Coating: Tuesday 11:00–12:00, 60 minutes. The parts then wait for the separately supplied inspection slot.
Wait for inspection: Tuesday 12:00–13:00, 60 minutes. Keep this interval separate from the inspection itself.
Final inspection: Tuesday 13:00–13:30, 30 minutes. The order reaches the example’s ready-for-dispatch endpoint at 13:30.
Wait for dispatch: Tuesday 13:30–14:00, 30 minutes. This is outside the selected production boundary.
Assumed transport: Tuesday 14:00–Wednesday 10:00, 1,200 minutes. The 20-hour interval and Wednesday receipt are illustrative transport inputs, not a guarantee or a universal shipping rule.
The intervals are consecutive and do not overlap. Keep each start beside the previous finish so another person can follow the chain. In a real record, mark whether each entry is an estimate, a confirmed booking or an actual event, and identify the evidence and checked time. A supplied transport assumption should remain visibly different from an observed customer receipt.
Reconcile the three totals
The processing total is 150 minutes, or 2½ hours: 60 cutting + 60 coating + 30 inspection. Waiting inside the selected production boundary is 1,560 minutes, or 26 hours: 1,500 before coating + 60 before inspection.
Add those two amounts to get 1,710 minutes, or 28½ hours, from Monday 09:00 release to Tuesday 13:30 ready for dispatch. The finish-minus-start check gives the same production elapsed time.
The whole order adds 60 minutes before release, 30 minutes before dispatch and 1,200 minutes of assumed transport: 60 + 1,710 + 30 + 1,200 = 3,000 minutes, or 50 hours. That matches Monday 08:00 to Wednesday 10:00.
Each total answers a different question. The 150-minute figure sums the selected work intervals. The 1,710-minute figure covers the specified shop passage. The 3,000-minute figure reaches the assumed customer endpoint. Put the boundaries beside the figures whenever you pass the record to someone else.
Test faster cutting with the same later bookings
Now cutting takes 30 minutes, from Monday 09:00 to 09:30. Every other booking and transport input stays unchanged. Coating still starts Tuesday 11:00, so the wait before it becomes 1,530 minutes, or 25½ hours.
Processing falls to 120 minutes, or two hours: 30 cutting + 60 coating + 30 inspection. Waiting within production becomes 1,590 minutes, or 26½ hours: 1,530 before coating + 60 before inspection. Together they still total 1,710 minutes.
Ready for dispatch remains Tuesday 13:30, dispatch remains 14:00 and assumed receipt remains Wednesday 10:00. The whole order still spans 3,000 minutes. The changed input has reduced processing by 30 minutes and increased waiting by the same amount under the fixed bookings.
The owner can now ask a concrete follow-up: is a different downstream booking available? The example supplies no earlier coating, inspection or transport slot. It therefore supports no earlier receipt calculation. Record any newly confirmed booking as a new version and rebuild the remaining chain from that point.
Stop when the next booking is missing
Return to the original one-hour cutting interval. Suppose coating now has a supplied slot of Tuesday 12:30–13:30. Its finish is 30 minutes after the original inspection start of 13:00. That inspection booking cannot follow coating in this example’s required sequence.
The record contains no replacement inspection slot. Leave inspection completion, ready-for-dispatch time, the later dispatch booking and revised receipt unresolved. The Tuesday 13:30 coating finish is known within this branch; it is not a completed-order time.
Do not shift every later timestamp by the 90-minute change in coating’s start. That would invent availability the record does not supply. Give the planner responsibility for confirming inspection and the shipping coordinator responsibility for the later transport inputs, with a next check time for each. This branch establishes a broken planning chain, without establishing a particular late delivery or missed contractual deadline.
Copy the five-line whole-order record
Use one version for the order and repeat the stage entry as needed. Keep the source calendar and confirmations with it.
Scope and clock. Order/revision ___ / required customer outcome ___ / start and end boundaries ___ / time zone ___ / estimate, booking or actual status ___ / checked time and evidence ___.
Serial stages. Operation ___ / required predecessor ___ / processing start and finish ___ / booking reference and status ___ / responsible person ___ / repeat for each stage ___.
Handoffs and waits. Previous finish ___ / next booked start ___ / waiting minutes ___ / boundary containing the interval ___ / missing readiness or booking evidence ___ / interval counted once ___.
Time bridge. Processing total ___ / waits inside production ___ / production elapsed total ___ / pre-release and downstream intervals ___ / whole-order end minus start ___ / units and discrepancy ___.
Decision and follow-through. Proposed completion and its assumptions ___ / missing next booking or receipt input ___ / person confirming it ___ / next check time ___ / original and revised versions ___.
Before discussing a revised customer date, ask the planner to point to the final booking that makes that date possible. If the evidence stops at coating, keep the answer there. The next useful action is to obtain the missing continuation, rather than turn an incomplete chain into a precise forecast.
An operation also needs the people required to perform it. Our guide to checking whether qualified operators cover the booked work handles that separate staffing question once the time windows are listed.
This guide is for general information and education. The fictional calendar illustrates a planning record and does not establish a delivery promise. Confirm your own inputs, bookings and customer arrangements before committing a date.