Two 75-minute jobs can fit on the shift calendar and still collide. In the fictional shop below, both jobs need a qualified operator for the whole time they run. They overlap for 40 minutes, and for the first 20 minutes of that overlap only one approved operator is available. A second person coming free at 10:05 helps the headcount then. The shop still needs someone who can take the second job from its 09:45 start.
Before you confirm both start times, put a name beside each job. Check that each person is available and approved for the work throughout the assigned block. If the same name comes up twice, lay those blocks on the same clock.
Record what each job needs
Start with the actual work order or revision. Write down the operation that needs an operator, the part of the schedule it occupies and how many people it requires at the same time. Use the interval the person must attend. A machine reservation and a staffed interval may have different boundaries. If the planner has only a machine booking, ask which parts of it actually require an operator before entering a staffing assumption.
Then open the roster beside the shop’s current approval record for that operation. In this example, “qualified” means current internal sign-off for the work shown. One record answers whether a person is approved for the operation. The other answers when the person is free. Keep the record version beside each entry and leave an unresolved approval or booking marked as such.
Google’s workforce scheduling example represents workers’ roles and skills separately from the number of people needed in each time window. It also separates requirements that must be met from preferences. Workforce Scheduling
For the fictional shop, having an approved person present for the whole block is a requirement. Keeping the earlier start for both jobs is the owner’s preference until it has been confirmed with the customer. Writing those down separately makes it clear which change the planner can explore if both original bookings cannot be staffed.
Check the two bookings on the same clock
All people, records and job times below are fictional. The shop uses Toronto time. Each job needs one approved person continuously. The shop does not switch operators partway through either job in this exercise.
Job A: 09:10 to 10:25, or 75 minutes.
Job B: 09:45 to 11:00, also 75 minutes.
Mira: Approved for the operation and available from 09:00 to noon.
Devon: Approved for the operation and available from 10:05 to 11:10 after another booking.
Lee: Available from 09:00 to noon. The file shows training, and the planner has yet to confirm current sign-off.
Take the later start and the earlier finish. Both jobs are running from 09:45 to 10:25. That is 40 minutes when the shop needs two approved people at once. From 09:45 to 10:05, only Mira is both free and approved. The shortfall in simultaneous coverage is one person for those 20 minutes.
Now check the whole interval for each assignment. Only Mira is eligible for all of A. Only Mira is eligible for all of B. Devon’s 10:05 availability misses the beginning of both bookings. Lee’s open calendar cannot settle the missing sign-off. The planning sheet offers one candidate for each job, yet the two entries refer to the same person. The original plan stays on hold.
Google’s employee scheduling example assigns one nurse to each shift and limits each nurse to one shift per day. Employee Scheduling
Here, the conflict is narrower than a day. The two jobs call for 150 attended minutes in total, and Mira has 180 free minutes on the calendar. Adding up person-hours would suggest room to spare. The overlap exposes the problem. Even after Devon comes free, that extra name cannot fill B from its original start under the fictional shop’s continuous-coverage requirement.
Test what would change the answer
Devon can cover B from its start
Suppose the scheduler clears Devon’s conflicting booking and confirms availability from 09:45 to 11:10. The shop lead verifies Devon’s current sign-off for the operation. Mira can cover A from 09:10 to 10:25, and Devon can cover B from 09:45 to 11:00. The same 40-minute overlap now has two distinct people assigned, and both assignments cover the full job. Record who cleared the earlier booking and which approval record the lead checked.
Devon is free, with sign-off still open
Use the earlier availability again, but suppose the record does not establish whether Devon’s approval is current for this work. The planner has a possible solution to follow up on. The assignment stays on hold until the shop lead verifies the approval or the planner can document another workable pair or time. Lee’s training entry still leaves an open question. Write down whose answer would change the plan so the item does not get lost at shift handoff.
B can move later
Return to the original conditions. The planner can ask whether B could start later while A stays at 09:10. A proposed B start at 10:25 clears the overlap, but Mira needs a stipulated 10-minute transition between the two jobs. Reserve 10:25 to 10:35 for that transition. B then runs from 10:35 to 11:50, still for 75 minutes.
B’s start and finish each move 50 minutes later. Mira has another 10 minutes before the noon end of her stated availability. The staffing check passes for that sequence if the revised booking and uninterrupted transition are confirmed. Ask the planner and customer to confirm the new window and check equipment, material, quality and downstream arrangements before committing. If machine or finishing capacity is now the constraint, see our guide to choosing a production mix.
Copy the planning worksheet
Give the schedule one version and put the job records, roster and approval record next to it. Repeat the first two rows as needed.
Job and required coverage. Order/revision ___ / station or operation ___ / attended start and finish ___ / people and approved role needed throughout ___ / basis for the time and coverage ___.
Named person. Name ___ / approval for this work and record version ___ / confirmed free from and until ___ / bookings or other conflicts ___ / missing evidence and who can confirm it ___.
Collision check. Shared time window ___ / number of approved people needed at once ___ / full-slot candidates for each job ___ / distinct assignment pair or uncovered interval ___.
Change to test. Relief available for the whole job or later job window ___ / transition time reserved ___ / bookings, approvals and revised time confirmed by ___ / other release checks still open ___.
Decision. Assign, replan or hold ___ / version and figures used ___ / who owns the next action ___ / when to check again ___.
Keep the original plan if a time or approval changes. Attach the revised roster and booking to the new version so the next person can see what made the assignment possible. Before either customer start is confirmed, a planner should be able to point to the person covering each job, the exact time they cover and the record that supports the assignment.
This guide is for general information and education. The fictional example illustrates a staffing decision. Confirm your own work requirements, internal approvals and available people before committing a schedule.