A customer needs 74 acceptable brackets. In the fictional shop below, the machine has 295 uncommitted minutes. The base plan takes 269 minutes, leaving 26 minutes to spare. An extra 30-minute fixture change makes that same order four minutes too long for the block. Settle which sequence the job requires before giving the customer a date.
The example checks the time occupied on one already operating machine. The shop still has to confirm materials, staffing and the work that follows machining. The figures are planning assumptions for a fictional Canadian manufacturer.
Find one open block on the actual calendar
Start with the machine, the shift and the order revision. Put the required number of acceptable parts beside the requested customer date. Open the station schedule and mark both the commitments already made and the periods when it cannot run. If an existing job has a provisional finish, flag that time for confirmation. It changes when your open block actually begins.
Vorne’s manufacturing method distinguishes planned production time from time actually running and treats changeovers during planned production as stops. Its quality measure divides first-pass good parts by the total parts produced. The worksheet borrows those timing and count distinctions for a booking decision. Vorne’s explanation of production time and good count
In the example, the shift runs from 06:30 to 14:00, Toronto time, for 450 minutes. The period from 06:30 to 07:15 is reserved for non-production work. Another order occupies the machine from 07:15 to 09:05. That leaves one open block from 09:05 to 14:00. Subtract 45 minutes and 110 minutes once to get 295 available minutes. There are no other unavailable periods within that block in this example.
Keep the actual start and end beside the subtraction. Two openings on either side of an occupied slot are two possible bookings. Joining them would require a different plan that accounts for stopping, restarting and any additional setup. This example keeps the order in one continuous block.
Separate fixed setup from occupied time per start
Check what the cycle measurement includes before using it. The Lean Enterprise Institute distinguishes machine cycle from an effective time that includes load and unload and allocates changeover time across pieces. It also treats customer lead time as broader than one operation. Lean Enterprise Institute’s cycle-time definitions
For this order, the shop stipulates three occupied station minutes per start, including the load and unload work that keeps the station busy. The first setup takes a separate 35 minutes. A timing sheet that already includes part of the setup needs a reconciliation before you add that setup again. The same check applies to a trial piece that appears in both the setup record and the cycle count.
Write down the start and stop points of the timing record and which fixture, material and part revision it represents. If a check can happen while the station runs, its time belongs in the appropriate readiness or downstream check. If it ties up the station, include the occupied interval once. The comparison needs station time on the same basis as the booking, so keep the timing record alongside the schedule.
Plan starts from the good-unit requirement
For this simplified job, the owner plans for first-pass acceptance. Each attempted bracket takes one cycle, including a bracket that fails the final check. The example sets rejected parts aside and has no rework loop. To check the basis for a planning yield, divide good first-pass units by total starts from the same completed group. Count acceptable parts against the agreed drawing and inspection rule.
The base plan uses a fictional 95% yield. Divide the required 74 acceptable brackets by 0.95 and round up to 78 whole starts. This is the number of starts to budget under that assumption. Keep the rate and its evidence or provisional status attached to the number so a second person can rerun the calculation. If the job uses a different revision or material, have the planner reassess the assumed yield before using it for a booking.
Check the same order three ways
Each branch keeps the 295-minute block, the same order for 74 acceptable brackets and the same three occupied minutes per start. Test each change on its own so you can see which input moves the decision.
Base sequence with one setup
Allow 78 starts at three minutes each, for 234 running minutes. Add the 35-minute setup to book 269 minutes. The run would use 09:05 to 13:34 on this plan. That leaves 26 minutes in the block. The scheduling lead can check the proposed reservation and the actual fixture sequence against that time.
A second fixture change is required
Keep the 95% assumption and the same 78 starts. Add a separately booked 30-minute change to the first 35 minutes of setup. Fixed time is now 65 minutes and running time remains 234 minutes. The booking would need 299 minutes, taking it to 14:04. That falls four minutes outside the block. The owner can ask the planner to confirm a different slot or sequence before committing the date.
Lower yield with the original sequence
Keep the original 35-minute setup but use an illustrative 88% yield. Dividing 74 by 0.88 and rounding up gives 85 starts. The machine needs 255 running minutes plus setup, for 290 minutes. The modeled finish is 13:55, with five minutes left. If the extra fixture change and lower yield could both apply, check them together before relying on either standalone result.
Copy the booking worksheet
Put the calendar and timing record next to this worksheet. Give each unresolved item a named person and a check time.
Order and station. Order and revision ___ / required acceptable units ___ / acceptance rule ___ / machine ___ / requested date ___.
Shift and booking. Shift start and end ___ / non-production periods ___ / prior reservations ___ / remaining continuous interval ___ / available minutes ___ / schedule reference ___.
Setup and cycle. Fixture sequence ___ / fixed setup and change minutes ___ / measured station minutes per start ___ / handling already included ___ / measurement reference ___.
Starts and machine time. Good/total counts or stated planning assumption ___ / whole starts rounded up ___ / running minutes ___ / total booked minutes ___ / headroom or gap ___.
Readiness and decision. Material, fixture and trained operator confirmed ___ / inspection, finishing, packing and dispatch checks ___ / reserve, replan or hold ___ / responsible person ___ / next review time ___.
Use the fifth line to decide what can be told to the customer. A station slot that fits may still need an available downstream inspection or dispatch time. If the acceptance counts behind the yield input are hard to trace, our guide to reconciling rework and scrap shows how to separate first-pass units from recovered parts and unresolved outcomes.
Before committing, ask the scheduler to confirm the 09:05 opening against the preceding order and the shop lead to confirm which fixture sequence applies. Give them the version of the worksheet you used. If either answer changes, keep the first calculation and record the updated booking against the new information. That makes it clear why the proposed date moved.
This guide is for general information and education. The fictional example illustrates a booking decision. Confirm your own operating inputs and prerequisites before committing a delivery date.